Project Background
The Sunset Plaza Drive Pipeline Replacement Project is a water system infrastructure improvement project that will replace approximately 1.2 miles of pipeline along Sunset Plaza Drive. The pipe is over 92 years old and needs to be replaced to improve water system reliability and enhance fire protection in the area.
LADWP crews will replace existing pipe with 6 and 8-inch steel pipe along Sunset Plaza Drive, Forest Knoll Drive, Sunset Plaza Terrace, Evanview Drive, and Viewsite Drive.
Construction Hours
Monday – Friday, 9:00 AM – 6:00 PM
Water service will not be interrupted during construction
Construction Schedule
Construction begins March 2020 and is scheduled to be completed by April 2021.